I have used Gardner Fibered Roof Coating to seal foundation below grade.   How long should I wait before replacing soil.  It is hot and would like to know if the tar will harden beforehand.
Not what you were looking for ? Try posting a question
Posted 2015-06-15T17:50:40+0000  by Lauri Lauri
 
Hi Lauri,

Once the coating is applied, allow at least 8 to 12 hours for it to congeal before replacing the soil. The amount of time allowed depends upon the outside temperature, the coating will congeal faster in cooler weather than in warm weather.

The easiest method is apply one day and replace the soil the next day.